Inspection Schedule for In-Ground & Above-Ground Pools


Office of the Newbury Building Inspector
Swimming Pool Installation Regulations
Inspection Schedule for In-Ground & Above--Ground Pools

In-Ground Pools:
1st Inspection EXCAVATION. After excavation is completed, and before any stone is placed in the bottom of excavation (if any is to be place).

2nd Inspection FRAME. After steel reinforcing or panels have been grounded, and after the grounding has been inspected by the wiring inspector and approved.

3rd Inspection CERTIFICATION. By a registered land surveyor an as built plot plan of the location of the structure most be submitted before work may continue (IF REQUIRED).

4th Inspection FINAL INSPECTION. After the required fencing, gates, and filters have been completed and installed correctly.

FILLING WITH WATER SHALL NOT BE STARTED UNTIL TEMPORARY OR PERMANENT FENCING IS COMPLETED.

Above-Ground Pools:
1st Inspection FRAME. After pool has been erected and after proper grounding has been inspected and approved by the wiring inspector, but before water is installed.

FILLING WITH WATER SHALL NOT BEGIN UNTIL LOCATION OF STRUCTURE HAS BEEN APPROVED
AND ALL NECESSARY FENCING HAS BEEN COMPLETED.

2nd Inspection FINAL INSPECTION - After the required fencing, gates, ladders, and filters have been installed correctly.

NOTE: Pool appurtenances such as Cabanas, Filters, Slides, Diving Boards, etc., are to be considered as a part of the structure and must be installed within the Town of Newbury Zoning Regulations.
A SEPARATE WIRING PERMIT MUST ALSO BE OBTAINED.